4-6 Barellan Ave, Carlingford

Location4-6 Barellan Ave
Site Area1850m²
ConstructionStrip footings - concrete in-fill slab - full brick
Project ObjectiveDevelopment
Construction Period8 months
Construction Value 2005$1.2 M
ClientJocon development
DesignerES Design
Completion Date2005

Project Details

This project was pure development. A subdivision of 2 blocks into 3, & later a subdivsion of each of the 3 into 2, producing 6 homes in total.

While most townhouse developments of this size are brick veneer, this particular market required full brick construction. With bulk excavation & piering required, large teams of concreters, bricklayers, plasterers & roofers were needed & co-ordinated in a manner to meet the tight completion schedule of 8 months.